Description
-
Model List:
- HD465-8E0 Dump Truck
- HD605-8E0 Dump Truck
- 1. Cover
- 2. Outline of separation (only for main components), Sales code7HC61
- 3. Outline of separation (only for main components), Sales code7HC62
- 4. Dimensions of main components, Sales code 7HC61
- 5. Dimensions of main components, Sales code 7HC62
- 6. Rough schedule of assembling and welding (for normal disassembly packing), Sales code 7HC61
- 7. Rough schedule of assembling and welding (for normal disassembly packing), Sales code 7HC62
- 8. Layout of work space, Sales code 7HC61
- 9. Layout of work space, Sales code 7HC62
- 10. Facility, jig and consumable parts list
- 11. Field assembly procedure
- 11.1. Oil, grease and coolant
- 11.2. Amount of oil, grease and coolant
- 11.3. Placing of bare machine
- 11.4. Placing of bare machine
- 11.5. Installation of L.H. front axle (connection of A arm)
- 11.6. Installation of tire and wheel assembly front
- 11.7. Installation of tire and wheel assembly rear
- 11.8. Installation of R.H. side mirror
- 11.9. Installation of R.H. platform mudguard
- 11.10. Installation of R.H. platform antenna
- 11.11. Installation of R.H. platform antenna pole
- 11.12. Installation of bumper step
- 11.13. Installation of radiator guard handrail
- 11.14. Installation of front under mirror
- 11.15. Installation of wheel chocks
- 11.16. Installation of battery under cover
- 11.17. Installation of L.H. catwalk mount
- 11.18. Installation of L.H. catwalk assembly
- 11.19. Installation of hand rail in front of cab
- 11.20. Installation of cab front handrail (with lighting lamp) 1
- 11.21. Installation of cab front handrail (with lighting lamp) 2
- 11.22. Installation of cab front handrail (with lighting lamp) 3
- 11.23. Installation of radio antenna
- 11.24. Connection of PLM harness
- 11.25. Installation of fender mudguard
- 11.26. Installation of exhaust pipe (Bodyheatingless specification)
- 11.27. Installation of dump body cab guard (HD605)
- 11.28. Mounting of dump body
- 11.29. Removal of hoist cylinder fixing jig
- 11.30. Installation of protection cover for welding a part in place
- 11.31. Installation and shim adjustment of dump body pad
- 11.32. Welding by actually positioning the dump body securing bracket on machine and shim adjustment
- 11.33. Detail of welding by actually positioning the dump body securing bracket on machine
- 11.34. Welding of exhaust pipe tube by actually positioning parts on machine HD465
- 11.35. Installation of dump body mudguards
- 11.36. Installation of dump body rock ejector and lock pin
- 11.37. Connection and adjustment of dump body angle sensor
- 11.38. Dump body control calibration
- 11.39. Air bleeding of hoist cylinder
- 11.40. Installation of dump body heating cover HD465
- 11.41. Installation of dump body heating cover HD605
- 11.42. Installation of grease piping(Autogreasing, 4point greasing)
- 11.43. Installation of grease piping to hinge
- 11.44. Sticking of dump body decal HD465
- 11.45. Sticking of dump body decal HD605
- 11.46. Adjustment of mirror angle
- 11.47. Check and adding of each oil, etc.
- 11.48. Adjustment of suspension gas
- 11.49. Method for checking and inflating tire
- 11.50. S010 Apply the additional work up to 30010.
- 11.51. C0010 Preparation of dump body welding
- 11.52. C0020 Assembly work of dump body
- 11.53. C0030 Tack welding of dump body
- 11.54. C0040 Dump body welding
- 11.55. C0050 Dump body welding procedure (1) (HD4658E0)
- 11.56. C0051 Dump body welding procedure (2) (HD4658E0)
- 11.57. C0060 Dump body welding procedure (3) (HD6058E0)
- 11.58. C0061 Dump body welding procedure (4) (HD6058E0)
- 11.59. C0070 Turning of dump body
- 11.60. C0080 Welding of dump body protector
- 11.61. C0090 Welding of dump body protector (HD4658E0)
- 11.62. C0091 Welding of dump body protector (HD6058E0)
- 11.63. C0100 Weld finishing and painting of dump body
- 12. Appendix Machine check sheet for field assembly